Dinnington market hall set for demolition before Christmas as revamp moves forward
Demolition of the indoor market is scheduled to start in mid-November and finish before Christmas, provided the remaining utility works are completed successfully.
Dinnington’s former indoor market is set to be knocked down before Christmas, with construction on the town centre’s regeneration scheme pencilled in for February.


The demolition will bring down a building that housed Dinnington’s indoor market for more than three decades.
In evidence submitted to the compulsory-purchase inquiry last year, its owners said the market traded from 1987 until its closure in 2020.
Rotherham Metropolitan Borough Council says the demolition is subject to the remaining utility works being completed.
Meanwhile, a new operator has been lined up to keep the Friday market trading after its previous operator pulled out.
The latest update sets out the next steps for the redevelopment, with three firms bidding for the main construction contract.
Demolition of the indoor market is scheduled to start in mid-November and finish before Christmas, provided the remaining utility works are completed successfully.
Northern Powergrid began its work in October and, according to the council, it is progressing as planned.
The authority hopes to appoint the main construction contractor in late November, subject to tender checks and approvals. The three bids are being assessed on quality, cost and social value.
A “Meet the Contractor” event is planned for early December, giving traders and other interested parties a chance to hear about the next phase.
Construction could begin in February 2027, although the council says an earlier start will be explored once a contractor is appointed.
For market traders, there are more immediate changes ahead.
The new operator will be granted a temporary six-month licence to manage the Friday market, which will stay in its current location until Christmas.
It will then move to a temporary street-market arrangement alongside the regeneration works. The council has bought new stalls and gazebos to help traders make the move.
The authority acknowledged concerns about communication, operating costs and the pressures facing town centre businesses. Officers have committed to being present during the transition and offering support where possible.
A longer-term plan for the market is also being developed.
The update comes as the project team deals with concerns about safety around utility works. Discussions are taking place to get affected areas reinstated and secured as quickly as possible.
The council said partners were also working together to tackle town centre anti-social behaviour.
In its update, the authority said: “We recognise that residents, traders and businesses are keen to see visible progress on site.”
It thanked them for their patience as the scheme moves towards demolition and construction.