Roadworks are dragging on - but residents say the contractors are doing their best
Roadworks are dragging on - but residents say the contractors are doing their best
Roadworks on a Kimberworth street are set to go on for many more weeks after they were due to be completed.
The work, to replace water mains, started in May and was supposed to be finished by the end of summer.
But residents have been told it will continue for another six weeks into November.
Farm View Road is split in two by the work so motorists cannot directly access one end from the other without a long detour.


Laying pipes has shifted along the road as work continues, blocking some drives and parking spaces as it goes.
Now, in a bid to get the work done more quickly, Yorkshire Water has pledged its contractors will be working longer hours.
But the stoic residents have told the Advertiser that while the work is a nuisance, they accept that the task of modernising pipes is badly needed.
Resident Graham Bennett said: “It’s been going on for a while and getting in the way.
“But if we ask them they will move their vehicles.
“People are just putting up with it.
“The contractors have a job to do. They are doing their best and are helping out the best they can.
“It has gone quite well.”


Mr Bennett said that the roadworks have hindered elderly people as they have stopped buses, and business deliveries have been made tricky too.
He said that he believed that the water pipes had not been replaced since the 1960s along the road so he welcomed the work to improve the water system.
Another local, who asked not to be named, added: “They said it would be finished by August. It’s gone on but we need to do the work.”
Couple Brian and Rhona Hampton were philosophical about the inconvenience of the work.
Mr Hampton said: “The contractors have been helpful. I have no complaints.”
Mrs Hampton added: “To be fair, we were fastened in for a while.
“But they are very obliging. They said they would get us out.
“You are notified if they need you to move your car.
“What we have found is that they are very good. Quite entertaining.”
But Mrs Hampton said that she had witnessed bad behaviour from exasperated motorists who had ignored roadworks signs.
“Someone was ramming the railings after going through the Road Closed signs,” she said.


A Yorkshire Water spokesperson said: “Our contractor, Galliford Try, have been working in the Kimberworth area to replace the rising main which serves our Droppingwell Road sewage pumping station.
“This work is vital investment to upgrade the local wastewater system by making it more resilient and reduce the likelihood of any flooding or pollution incidents.
“We’ve been working closely with the council’s highways teams to address concerns about congestion in the area after listening to feedback from the local community.
“As a result, we’re going to be extending the working hours of our site team to help speed up the work we’re doing so we’ll hopefully be finished earlier.
“Work will take place between 7am and 6pm, Monday to Thursday, and between 7am and 4pm on Fridays and Saturdays.
“We’d like to thank local residents for their continued patience and understanding while we carry out this important upgrade to the wastewater network and apologise for any inconvenience caused.”
.jpeg?trim=54,0,55,0&crop=&width=640&quality=65)

Andrew Bramidge, executive director for regeneration and environment at Rotherham Council, confirmed that the local authority has discussed a strategy of work with Yorkshire Water to ease difficulties.
Mr Bramidge said: “We recognise that the Yorkshire Water roadworks has been disruptive for residents living on Farm View Road and surrounding streets and understand the frustration that long-running work can cause.
“The council has had regular discussions with Yorkshire Water and its contractor since the project started in May and have requested that affected residents are kept informed of progress and timescales.
“Yorkshire Water will be delivering letters to impacted residents outlining the planned phasing of the works and the expected timetable for delivery.
“We have also asked for work at the junction of Farm View Road and Webster Crescent to be prioritised to improve access and provide an alternative route while road closures are in place.
“We’ve also requested extended working hours during the week and additional Saturday working to help accelerate progress.
“A number of emergency repairs to burst water mains and electrical cable faults have affected the programme, but all works, including permanent reinstatement, are expected to be completed by the end of November.”