Major flood defence scheme could be in place by 2028

RISK of future flooding in Catcliffe and Treeton may be effectively wiped out by plans to remove a bottleneck on the River Rother - and the work may be completed as early as 2028.

Rotherham Council has identified that increasing the gap below Treeton bridge by just 900mm would answer the problem of water backing up and overtopping the river, even during an extreme one-in-200-year event.

Aftermath: Council leader Chris Read in Catcliffe after Storm Babetplaceholder image
Aftermath: Council leader Chris Read in Catcliffe after Storm Babet

The council has already set aside £6m for the project but it is acknowledged that over the course of a long-term project - with a completion date expected between 2028 and 2030 - there is the possibility of costs rising.

That could be due to inflation, unforeseen problems with groundworks and other factors.

It is also a technically challenging project, with few contractors qualified to carry out the work.

As such, the council’s Cabinet, made up of senior councillors, is being asked to approve progress which would likely see a contractor appointed by the Spring of next year.

It is suggested that one company to both design and build the new structure would “streamline delivery by integrating design and construction under one contractor, thereby improving co-ordination and reducing programme risk,” according to a council report.

That would allow development work to press ahead, leading to the removal of the existing bridge structure and its replacement with a modern equivalent, providing the required extra 900mm clearance.

Some work, on foundations, would need to be done during summer months, when river levels are expected to be low.

However, the bridge itself would be constructed off-site and lifted into position.

During development work, the council explored the impact of removing the bridge altogether, but found that had no measurable impact of reducing the probability of future flooding.

The council has already been working closely with the Environment Agency on work to tackle flooding issues and they expect “ongoing collaboration” with the agency “throughout the lifecycle of the project.”

Catcliffe has been hit by three flooding events this century, with the most recent caused by Storm Babet just over two years ago when 148 homes in the village, and Treeton were flooded, along with five businesses.

More than 90 were flooded in 200, with up to 250 affected in 2008.

The Cabinet meets on November 17 to consider the report.